SAFE-SP · Question #44
Which statement is true about the PI Planning event?
The correct answer is C. It involves everyone in the program over a two-day period. PI Planning is a face-to-face event that brings everyone in the Agile Release Train (ART) together - all teams, Product Management, System Architects, Business Owners, and other stakeholders - over a two-day period to align on a common mission and plan the next Program…
Question
Which statement is true about the PI Planning event?
Options
- AIt involves only the team members who are most qualified to estimate the work
- BIt involves program Portfolio Management to prioritize the Stories presented by teams during the
- CIt involves everyone in the program over a two-day period
- DIt involves Product Management and Product Owners on the first day and the rest of the teams on
How the community answered
(25 responses)- A4% (1)
- C92% (23)
- D4% (1)
Explanation
PI Planning is a face-to-face event that brings everyone in the Agile Release Train (ART) together - all teams, Product Management, System Architects, Business Owners, and other stakeholders - over a two-day period to align on a common mission and plan the next Program Increment, making C correct.
- A is wrong because PI Planning is explicitly not limited to qualified estimators - broad participation across all roles is a core principle, ensuring shared understanding and commitment.
- B is wrong because Portfolio Management does not prioritize Stories during PI Planning; that level operates on Epics and strategic themes, not team-level Stories.
- D is wrong because there is no split where Product Management/POs attend Day 1 alone - all participants are present throughout both days, though the agenda does have structured phases.
Memory tip: Think of PI Planning as the ART's "all-hands kickoff" - the word everyone in option C mirrors SAFe's emphasis on full-team alignment and collective ownership over the planning horizon.