SAFE-SP · Question #18
Which statement is true about Iteration Planning?
The correct answer is B. It is required for every Iteration to enable fast learning cycles. Iteration Planning is a mandatory ceremony held at the start of every Iteration (sprint), serving as the foundation for fast learning cycles by allowing teams to inspect, adapt, and commit to a focused set of work - making B correct. A is wrong because in Agile, work items are…
Question
Which statement is true about Iteration Planning?
Options
- AItems are assigned to the team members
- BIt is required for every Iteration to enable fast learning cycles
- CThe PO does not need to attend
- DIt occurs on the last day of the Iteration
How the community answered
(40 responses)- A3% (1)
- B88% (35)
- C8% (3)
- D3% (1)
Explanation
Iteration Planning is a mandatory ceremony held at the start of every Iteration (sprint), serving as the foundation for fast learning cycles by allowing teams to inspect, adapt, and commit to a focused set of work - making B correct. A is wrong because in Agile, work items are self-assigned by the team collectively, not distributed by a manager or leader. C is wrong because the Product Owner's attendance is essential - they clarify priorities, answer questions about backlog items, and accept team commitments. D is wrong because Iteration Planning occurs at the beginning of the Iteration, not the end (that's the Iteration Review/Retrospective).
Memory tip: Think of Iteration Planning as the "kickoff meeting" - it always opens the Iteration, it's never optional, and everyone who owns the what (PO) and the how (team) must be present.
Topics