nerdexam
BCS-ISEB

RE18 · Question #80

The business analyst for a project has elicited, analysed and documented the requirements of the identified stakeholders; these have been validated and agreed. A few days after this agreement took…

The correct answer is C. Ask the project manager to submit a change request for the required changes. Exam Questions, Study Guides, Practice Tests. Lead the way to help you pass any IT Certification exams, 100% Pass Guaranteed or Full Refund. Especially CiscoVendor: BCS Exam Name: BCS Practitioner Certificate in Requirements Engineering 2018 Version: 20.071 Juniper, Check…

Requirements Management

Question

The business analyst for a project has elicited, analysed and documented the requirements of the identified stakeholders; these have been validated and agreed. A few days after this agreement took place, the project manager approached the analyst with a request to change several requirements. What course of action SHOULD. the business analyst take?

Options

  • AAccept the request of the project manager and change the requirements.
  • BAsk all stakeholders whether they agree to the requested changes.
  • CAsk the project manager to submit a change request for the required changes.
  • DReject the project manager's request to make changes to the requirements.

How the community answered

(37 responses)
  • A
    11% (4)
  • B
    5% (2)
  • C
    81% (30)
  • D
    3% (1)

Explanation

Exam Questions, Study Guides, Practice Tests. Lead the way to help you pass any IT Certification exams, 100% Pass Guaranteed or Full Refund. Especially CiscoVendor: BCS Exam Name: BCS Practitioner Certificate in Requirements Engineering 2018 Version: 20.071 Juniper, Check Point, LPI, Nortel, EXIN and so on. Our Slogan: First Test, First Pass. Help you to pass any IT Certification exams at the first try. You can reach us at any of the email addresses listed below. Any problems about IT certification or our products, you could rely upon us, we will give you satisfactory answers in 24 hours.

Topics

#change management#change request process#requirements baseline#stakeholder agreement

Community Discussion

No community discussion yet for this question.

Full RE18 Practice