Several requirements have been elicited in a project. One of them specifies the need for the system to download overnight, to a central repository, all the transactions made during the day in the…
The correct answer is A. Prototype. See the full explanation below for the reasoning.
Question
Several requirements have been elicited in a project. One of them specifies the need for the system to download overnight, to a central repository, all the transactions made during the day in the remote offices. The project team is not sure that this is technically possible. What might help them to analyse this requirement?
Options
- APrototype.
- BStructured walkthrough.
- CScenario analysis.
- DRequirements catalogue.