The following two requirements have been captured during elicitation: REQ#1: The system will operate during standard working hours, 5 days a week (Monday to Friday) | Priority = S(houl(d). Source =…

The correct answer is A. Resolution fields of REQ#1 and REQ#2 with the decision of the operations director. See the full explanation below for the reasoning.

Question

The following two requirements have been captured during elicitation: REQ#1: The system will operate during standard working hours, 5 days a week (Monday to Friday) | Priority = S(houl(d). Source = Operations assistant. REQ#2: The system will operate during extended working hours, 6 days a week (Monday to Saturday) | Priority = S(houl(d). Source = Operations supervisor. The owner of these requirements (the operations director) is content that REQ#1 and REQ#2 should be replaced by: REQ#99 - The system must operate from 06:00 to 20:00, Monday to Saturday. What update to the requirements catalogue is needed to reflect this change?

Options

  • AResolution fields of REQ#1 and REQ#2 with the decision of the operations director.
  • BSource of REQ#1 and REQ#2 to Operations Director.
  • CRationale field of REQ#1 and REQ#2 to indicate merged requirements.
  • DPriority of REQ#99 to M(ust) to reflect the merger of two S(houl(d) requirements.

How the community answered

(26 responses)
  • A
    81% (21)
  • B
    12% (3)
  • C
    4% (1)
  • D
    4% (1)