Below is a list of common requirements elicitation techniques: (a) Workshops. (b) Prototyping. (c) Scenario analysis. (d) Interviews. (e) Document analysis. (f) Activity sampling. Which of them are…
The correct answer is A. a, c and d only. See the full explanation below for the reasoning.
Question
Below is a list of common requirements elicitation techniques: (a) Workshops. (b) Prototyping. (c) Scenario analysis. (d) Interviews. (e) Document analysis. (f) Activity sampling. Which of them are suitable methods for use in both linear and agile projects?
Options
- Aa, c and d only.
- Ba, c and e only.
- Cb, c and f only.
- Dd, e and f only.
How the community answered
(48 responses)- A81% (39)
- B4% (2)
- C13% (6)
- D2% (1)