RE18 · Question #54

Below is a list of common requirements elicitation techniques: (a) Workshops. (b) Prototyping. (c) Scenario analysis. (d) Interviews. (e) Document analysis. (f) Activity sampling. Which of them are…

The correct answer is A. a, c and d only. See the full explanation below for the reasoning.

Question

Below is a list of common requirements elicitation techniques: (a) Workshops. (b) Prototyping. (c) Scenario analysis. (d) Interviews. (e) Document analysis. (f) Activity sampling. Which of them are suitable methods for use in both linear and agile projects?

Options

  • Aa, c and d only.
  • Ba, c and e only.
  • Cb, c and f only.
  • Dd, e and f only.

How the community answered

(48 responses)
  • A
    81% (39)
  • B
    4% (2)
  • C
    13% (6)
  • D
    2% (1)