BCS-ISEB
RE18 · Question #49
A car manufacturer wishes to understand what customers want from its cars. Consequently, it has invited one hundred customers to a series of meetings, where they will explore new technology and…
The correct answer is B. Focus Group. See the full explanation below for the reasoning.
Question
A car manufacturer wishes to understand what customers want from its cars. Consequently, it has invited one hundred customers to a series of meetings, where they will explore new technology and generate ideas for future developments and directions. The outcomes of these meetings will be considered by the team responsible for new car development. Which requirements elicitation technique is going to be used?
Options
- ASurvey.
- BFocus Group.
- CActivity sample.
- DWorkshop.
How the community answered
(41 responses)- A2% (1)
- B83% (34)
- C10% (4)
- D5% (2)
Community Discussion