BCS-ISEB
RE18 · Question #42
A senior developer has been asked to ensure that all requirements in a requirements document are technically feasible. At which stage of the requirements engineering framework is the project?
The correct answer is B. Validation. See the full explanation below for the reasoning.
Question
A senior developer has been asked to ensure that all requirements in a requirements document are technically feasible. At which stage of the requirements engineering framework is the project?
Options
- AAnalysis.
- BValidation.
- CDocumentation.
- DManagement.
How the community answered
(37 responses)- A5% (2)
- B84% (31)
- C8% (3)
- D3% (1)
Community Discussion
No community discussion yet for this question.