A project, which was initiated several months ago, has been impacted by the following changes: 1. An organizational restructure has altered the responsibilities of the stakeholders. 2. A new chief…
The correct answer is B. Priority, owner, version history. See the full explanation below for the reasoning.
Question
A project, which was initiated several months ago, has been impacted by the following changes: 1. An organizational restructure has altered the responsibilities of the stakeholders. 2. A new chief executive has been appointed, who has new ideas regarding the immediate focus of the project. Which of the following attributes in a requirements catalogue entry would need to be updated to reflect these changes?
Options
- AOwner, source.
- BPriority, owner, version history.
- CRationale, priority, source.
- DVersion history, author, rationale.
How the community answered
(22 responses)- A5% (1)
- B73% (16)
- C5% (1)
- D18% (4)
Community Discussion
No community discussion yet for this question.