A business analyst has interviewed project stakeholders and has a robust list of requirements. At which stages in the requirements engineering framework would he check that these requirements…

The correct answer is B. Elicitation and analysis. See the full explanation below for the reasoning.

Question

A business analyst has interviewed project stakeholders and has a robust list of requirements. At which stages in the requirements engineering framework would he check that these requirements support the business objectives defined at the start of the project?

Options

  • AAnalysis and validation
  • BElicitation and analysis
  • CElicitation and documentation
  • DValidation and documentation

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    83% (19)
  • C
    4% (1)
  • D
    9% (2)