Question

A business analyst working on a project has been informed that changes are required in a particular requirement; she has revisited the requirement set and is unable to determine other requirements that might be impacted by such changes. Which element of requirements management appears to be missing?

Options

  • AChange control
  • BRequirements cross-referencing
  • CRequirements identification
  • DRequirements origin and ownership