Question
A business analyst working on a project has been informed that changes are required in a particular requirement; she has revisited the requirement set and is unable to determine other requirements that might be impacted by such changes. Which element of requirements management appears to be missing?
Options
- AChange control
- BRequirements cross-referencing
- CRequirements identification
- DRequirements origin and ownership
How the community answered
(35 responses)- A9% (3)
- B3% (1)
- C71% (25)
- D17% (6)
Community Discussion