A business analyst working on a project has been informed that changes are required in a particular requirement; she has revisited the requirement set and is unable to determine other requirements…

The correct answer is C. Requirements identification. See the full explanation below for the reasoning.

Question

A business analyst working on a project has been informed that changes are required in a particular requirement; she has revisited the requirement set and is unable to determine other requirements that might be impacted by such changes. Which element of requirements management appears to be missing?

Options

  • AChange control
  • BRequirements cross-referencing
  • CRequirements identification
  • DRequirements origin and ownership

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    71% (25)
  • D
    17% (6)