RE18 · Question #25
A project sponsor has been asked to validate requirements in the requirements validation stage of the requirements engineering framework. The primary validation role of the project sponsor is to…
The correct answer is B. Compliant with quality standards and policies. See the full explanation below for the reasoning.
Question
A project sponsor has been asked to validate requirements in the requirements validation stage of the requirements engineering framework. The primary validation role of the project sponsor is to ensure that the requirements are what at this stage?
Options
- AAligned with business objectives.
- BCompliant with quality standards and policies.
- CTechnically feasible.
- DUnambiguous.
How the community answered
(40 responses)- A18% (7)
- B73% (29)
- C3% (1)
- D8% (3)
Community Discussion
No community discussion yet for this question.