A business analyst is in the process of completing the requirements document for a project. She has made the following 'to-do' list of actions to help keep track of her work: 1. Need to amend the…
The correct answer is C. Requirements catalogue and data model. See the full explanation below for the reasoning.
Question
A business analyst is in the process of completing the requirements document for a project. She has made the following 'to-do' list of actions to help keep track of her work: 1. Need to amend the description of the scope of the project. 2. Need to record the terminology used throughout the document. 3. Need to add the use cases and the as-is business process diagrams. When she completes all of these actions, which requirements document sections will not have been updated?
Options
- AData models and introduction and background.
- BFunction models and requirements catalogue.
- CRequirements catalogue and data model.
- DRequirements catalogue and glossary of terms.
How the community answered
(41 responses)- A15% (6)
- B7% (3)
- C73% (30)
- D5% (2)