BICSI
RCDDV15 · Question #311
RCDDV15 Question #311: Real Exam Question with Answer & Explanation
The correct answer is B. Gantt Chart D. Critical Path Method (CPM). See the full explanation below for the reasoning.
Question
When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams to integrate logical activities and identify critical paths on the project? (Select two options.)
Options
- AIf This Then That (IFTT)
- BGantt Chart
- CWork Breakdown Structure (WBS)
- DCritical Path Method (CPM)
- EProgram Evaluation Review Technique (PERT)
Community Discussion
No community discussion yet for this question.