When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams to integrate logical activities and identify…

The correct answer is B. Gantt Chart D. Critical Path Method (CPM). There appears to be an error in the provided answer key. Based on the question's criteria - network diagrams + critical path identification - the correct answers are D and E, not B and D. Why D (CPM) and E (PERT) are correct: Both Critical Path Method and Program Evaluation…

Project Planning and Scheduling

Question

When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams to integrate logical activities and identify critical paths on the project? (Select two options.)

Options

  • AIf This Then That (IFTT)
  • BGantt Chart
  • CWork Breakdown Structure (WBS)
  • DCritical Path Method (CPM)
  • EProgram Evaluation Review Technique (PERT)

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    70% (14)
  • C
    20% (4)
  • E
    5% (1)

Explanation

There appears to be an error in the provided answer key. Based on the question's criteria - network diagrams + critical path identification - the correct answers are D and E, not B and D.

Why D (CPM) and E (PERT) are correct: Both Critical Path Method and Program Evaluation Review Technique use network diagrams (nodes and arrows representing task dependencies) to map activity sequences and identify the critical path - the longest chain of dependent tasks that determines the minimum project duration. These are the two classic network-based scheduling techniques in project management.

Why the distractors are wrong:

  • A (IFTTT): An automation web tool ("If This Then That") - completely unrelated to project scheduling.
  • B (Gantt Chart): Uses a horizontal bar chart to display task timelines, not a network diagram. It cannot inherently show dependencies or calculate critical paths without additional tools.
  • C (WBS): A hierarchical decomposition of project deliverables/scope - it organizes what needs to be done, but contains no network diagram or scheduling logic.

Memory tip: Think "Network = CPM + PERT" - the two methods that draw networks of activity arrows. Gantt is a bar chart (bars, not networks). If your exam source marks B and D as correct, flag it - this appears to be a typo where E was swapped for B.

Topics

#project scheduling methods#network diagrams#critical path analysis#ICT project management