nerdexam
BICSI

RCDDV15 · Question #311

RCDDV15 Question #311: Real Exam Question with Answer & Explanation

The correct answer is B. Gantt Chart D. Critical Path Method (CPM). See the full explanation below for the reasoning.

Question

When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams to integrate logical activities and identify critical paths on the project? (Select two options.)

Options

  • AIf This Then That (IFTT)
  • BGantt Chart
  • CWork Breakdown Structure (WBS)
  • DCritical Path Method (CPM)
  • EProgram Evaluation Review Technique (PERT)

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice