nerdexam
BICSI

RCDDV15 · Question #297

In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations recently, the customer decides that there is no need to continue phase gate…

The correct answer is C. Continue periodic gate reviews to maintain program effectiveness for benefits realization. See the full explanation below for the reasoning.

Program Governance and Performance

Question

In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations recently, the customer decides that there is no need to continue phase gate reviews. What should the program manager do next?

Options

  • AAsk the stakeholders what they want and proceed with their recommendations
  • BAgree with the customer and Initiate change control procedures
  • CContinue periodic gate reviews to maintain program effectiveness for benefits realization
  • DReplace program reviews with periodic communications of the program's status

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    14% (5)
  • C
    78% (29)
  • D
    3% (1)

Topics

#program governance#phase gate reviews#benefits realization#stakeholder management

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice