What's the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)
The correct answer is B. 610 mm (24 in) E. Below the area's 50-year frost line. See the full explanation below for the reasoning.
Outside Plant Pathway Systems
Question
What's the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)
Options
- A305 mm(12 in)
- B610 mm (24 in)
- C914 mm (36 in)
- D1270 mm (50 in)
- EBelow the area's 50-year frost line
How the community answered
(25 responses)- A16% (4)
- B76% (19)
- C4% (1)
- D4% (1)
Topics
#trench depth#underground burial#frost line#outside plant installation