nerdexam
BICSI

RCDDV15 · Question #27

What's the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)

The correct answer is B. 610 mm (24 in) E. Below the area's 50-year frost line. See the full explanation below for the reasoning.

Outside Plant Pathway Systems

Question

What's the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)

Options

  • A305 mm(12 in)
  • B610 mm (24 in)
  • C914 mm (36 in)
  • D1270 mm (50 in)
  • EBelow the area's 50-year frost line

How the community answered

(25 responses)
  • A
    16% (4)
  • B
    76% (19)
  • C
    4% (1)
  • D
    4% (1)

Topics

#trench depth#underground burial#frost line#outside plant installation

Community Discussion

No community discussion yet for this question.