RCDDV15 Question #25: Real Exam Question with Answer & Explanation

The correct answer is C. 3.90 dB. See the full explanation below for the reasoning.

Question

An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building A. Both ends are terminated with SC connectors. What is the loss budget for the above fiber link?

Options

  • A2.95 dB
  • B3.40dB
  • C3.90 dB
  • D4.35 dB

Community Discussion