What is the expected life cycle, in years, of building automation system within a building structure with a life cycle of 40+ years?

The correct answer is C. 5 to 7. Building automation systems (BAS) have a much shorter life cycle than the buildings they serve, typically requiring replacement or major upgrades every 5 to 7 years due to technology obsolescence.

Special Applications

Question

What is the expected life cycle, in years, of building automation system within a building structure with a life cycle of 40+ years?

Options

  • A1 to 2
  • B2 to 4
  • C5 to 7
  • D8 to 12
  • E12 to 15

How the community answered

(59 responses)
  • A
    10% (6)
  • B
    5% (3)
  • C
    81% (48)
  • D
    2% (1)
  • E
    2% (1)

Why each option

Building automation systems (BAS) have a much shorter life cycle than the buildings they serve, typically requiring replacement or major upgrades every 5 to 7 years due to technology obsolescence.

A1 to 2

A 1-to-2-year life cycle reflects consumer electronics turnover, not enterprise-grade building automation controllers and field devices.

B2 to 4

A 2-to-4-year cycle is too short for commercial BAS deployments, which carry significant installation and commissioning costs that require longer amortization.

C5 to 7Correct

BAS components including controllers, sensors, and software platforms become obsolete on a 5-to-7-year cycle as technology evolves, vendor support ends, and integration with newer building systems becomes necessary. This stands in contrast to the structural building life cycle of 40+ years, requiring multiple BAS generations over a building's lifetime. Industry standards and BICSI guidelines recognize this layered life-cycle model for infrastructure planning.

D8 to 12

An 8-to-12-year cycle overstates BAS longevity, as software support, network protocol compatibility, and component availability typically degrade well before that point.

E12 to 15

A 12-to-15-year cycle is more aligned with mechanical plant equipment life cycles rather than the electronic control and communication layers of a BAS.

Concept tested: Building automation system infrastructure life cycle planning

Source: https://www.bicsi.org/standards/available-standards-store/single-document/bicsi-007-2022-information-technology-systems-design-and-implementation-best-practices-for-healthcare-institutions

Topics

#BAS life cycle#system planning#building lifespan#replacement cycle

Community Discussion

No community discussion yet for this question.

Full RCDD Practice