When planning a telecommunication termination area, what is the estimated space needed to terminate 144 strands of optical fiber?
The correct answer is B. 7315.21 mm2 (288 in2). Option B is correct because industry standards (BICSI TDMM) allocate 2 square inches per fiber strand for termination space planning. Multiplying 144 strands × 2 in² yields exactly 288 in² (7315.21 mm²), making B the precise match. The distractors are wrong because they…
Question
When planning a telecommunication termination area, what is the estimated space needed to terminate 144 strands of optical fiber?
Options
- A6350.01 mm2 (250 in2)
- B7315.21 mm2 (288 in2)
- C8890.01 mm2 (350 in2)
- D10972.82 mm2 (432 in2)
- E14376.43 mm2 (566 in2)
How the community answered
(28 responses)- A4% (1)
- B82% (23)
- D11% (3)
- E4% (1)
Explanation
Option B is correct because industry standards (BICSI TDMM) allocate 2 square inches per fiber strand for termination space planning. Multiplying 144 strands × 2 in² yields exactly 288 in² (7315.21 mm²), making B the precise match.
The distractors are wrong because they correspond to different per-strand ratios that don't match the standard: A (250 in²) falls short of the 288 in² requirement; C (350 in²) overshoots by roughly 62 in²; D (432 in²) would correspond to a 3 in² per strand allocation; and E (566 in²) is nearly double the required space, more appropriate for a much larger fiber count or additional equipment.
Memory tip: Think "2 square inches per fiber" - for 144 strands, pair each fiber with 2 in², then group them: 144 × 2 = 288. If you remember that a standard fiber patch panel row holds 12 fibers × 2 in² = 24 in² per row, 144 fibers = 12 rows × 24 in² = 288 in².