You are working on the design of a new, large ER/TR that will contain many racks and data cabinets including a large UPS system. Your recommendation to the architect for room access from inside the…

The correct answer is E. One double door with a removable center post. See the full explanation below for the reasoning.

Question

You are working on the design of a new, large ER/TR that will contain many racks and data cabinets including a large UPS system. Your recommendation to the architect for room access from inside the building is:

Options

  • ATwo 0.9 m (3 ft) solid doors
  • BOne 1.5 m (5 ft) metallic roll top door
  • COne 1.2 m (4 ft) solid core, steel sheath door
  • DOne 1.83 m (6 ft) solid core dual direction sliding door with removable sides
  • EOne double door with a removable center post

How the community answered

(42 responses)
  • A
    2% (1)
  • C
    5% (2)
  • D
    10% (4)
  • E
    83% (35)