RCDD-001 · Question #60
A campus backbone design linking two buildings requires that you install a high-fiber-count cable very quickly, using the conduit system provided. Cost is not so much an issue as urgency is to meet…
The correct answer is E. Single sheathed cable equipped with preconnectorized assemblies. See the full explanation below for the reasoning.
Question
A campus backbone design linking two buildings requires that you install a high-fiber-count cable very quickly, using the conduit system provided. Cost is not so much an issue as urgency is to meet a service demand. Your first choice of fiber cable installation is to use:
Options
- AMultiple sheathed cables with field connectorization
- BMultiple sheathed cables using pigtail connectorization
- CSingle high fiber count sheathed cable with field connectorization
- DSingle sheathed high-fiber-count cable with pigtail connectorization
- ESingle sheathed cable equipped with preconnectorized assemblies
How the community answered
(22 responses)- A5% (1)
- B9% (2)
- C5% (1)
- E82% (18)