What type of estimate is based on the cost of performing similar work in the past, adjusted for current job conditions?

The correct answer is A. Analogous. See the full explanation below for the reasoning.

Question

What type of estimate is based on the cost of performing similar work in the past, adjusted for current job conditions?

Options

  • AAnalogous
  • BParametric
  • CEngineering
  • DLedger
  • EPERT