BICSI
RCDD-001 · Question #174
What is the PERT estimate (in hours) for project design where: - Optimistic time is 40 hours - Most likely time is 50 hours - Pessimistic time is 60 hours
The correct answer is C. 50 hours. See the full explanation below for the reasoning.
Question
What is the PERT estimate (in hours) for project design where:
- Optimistic time is 40 hours
- Most likely time is 50 hours
- Pessimistic time is 60 hours
Options
- A40 hours
- B45 hours
- C50 hours
- D55 hours
- E60 hours
How the community answered
(37 responses)- A3% (1)
- B3% (1)
- C70% (26)
- D11% (4)
- E14% (5)
Community Discussion
No community discussion yet for this question.