What is the PERT estimate (in hours) for project design where: - Optimistic time is 40 hours - Most likely time is 50 hours - Pessimistic time is 60 hours

The correct answer is C. 50 hours. See the full explanation below for the reasoning.

Question

What is the PERT estimate (in hours) for project design where:

  • Optimistic time is 40 hours
  • Most likely time is 50 hours
  • Pessimistic time is 60 hours

Options

  • A40 hours
  • B45 hours
  • C50 hours
  • D55 hours
  • E60 hours

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    70% (26)
  • D
    11% (4)
  • E
    14% (5)