If a work breakdown structure (WBS) shows the tasks below, what is C, the successor task?
The correct answer is A. Hold inspection. See the full explanation below for the reasoning.
Question
If a work breakdown structure (WBS) shows the tasks below, what is C, the successor task?
Options
- AHold inspection
- BCreate budget
- CConduct safety meeting
- DPerform site survey
How the community answered
(34 responses)- A79% (27)
- B6% (2)
- C12% (4)
- D3% (1)