All of the following are true about the post construction phase EXCEPT:

The correct answer is A. The owner is responsible to update the record copy drawings to reflect "as-built" documents. See the full explanation below for the reasoning.

Question

All of the following are true about the post construction phase EXCEPT:

Options

  • AThe owner is responsible to update the record copy drawings to reflect "as-built" documents.
  • BThe contractors are resolving issues identified on the punch lists.
  • CThe architect is involved in final acceptance and contract closeout activities.
  • DThe construction manager is coordinating removal of construction equipment and job trailers.

How the community answered

(48 responses)
  • A
    73% (35)
  • B
    17% (8)
  • C
    6% (3)
  • D
    4% (2)