BICSI
RCDD-001 · Question #166
All of the following are true about the post construction phase EXCEPT:
The correct answer is A. The owner is responsible to update the record copy drawings to reflect "as-built" documents. See the full explanation below for the reasoning.
Question
All of the following are true about the post construction phase EXCEPT:
Options
- AThe owner is responsible to update the record copy drawings to reflect "as-built" documents.
- BThe contractors are resolving issues identified on the punch lists.
- CThe architect is involved in final acceptance and contract closeout activities.
- DThe construction manager is coordinating removal of construction equipment and job trailers.
How the community answered
(48 responses)- A73% (35)
- B17% (8)
- C6% (3)
- D4% (2)
Community Discussion
No community discussion yet for this question.