Question
At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?
Options
- AThe project is ahead of schedule.
- BThe project is over budget.
- CThe project is behind schedule.
- DThe project is under budget.