At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?
The correct answer is A. The project is ahead of schedule. See the full explanation below for the reasoning.
Question
At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?
Options
- AThe project is ahead of schedule.
- BThe project is over budget.
- CThe project is behind schedule.
- DThe project is under budget.
How the community answered
(38 responses)- A74% (28)
- B16% (6)
- C8% (3)
- D3% (1)