ASIS
PSP · Question #120
A good risk management program involves:
The correct answer is D. All of the above. See the full explanation below for the reasoning.
Question
A good risk management program involves:
Options
- AIdentify risks or specific vulnerabilities
- BAnalyze and study risks, including likelihood and degree of danger of an event
- CStudy of security programs
- DAll of the above
How the community answered
(37 responses)- A5% (2)
- B3% (1)
- C8% (3)
- D84% (31)
Community Discussion
No community discussion yet for this question.