PSM-II · Question #145

Peter, a Project Manager, has raised concerns about your Scrum Team's productivity and progress towards the objectives. Which is the best way to respond to Peter's concerns?

The correct answer is A. Share the Product Backlog, the projections towards the release dates and ensure that Peter has. One of the key pillars that support the empirical process control is Transparency. Transparency will help manage stakeholder expectations and allow the teams to effectively adapt if and when

Facilitating

Question

Peter, a Project Manager, has raised concerns about your Scrum Team's productivity and progress towards the objectives. Which is the best way to respond to Peter's concerns?

Options

  • AShare the Product Backlog, the projections towards the release dates and ensure that Peter has
  • BShow the Profit & Loss (P&L) report.
  • CShare the current impediments.
  • DShare the last stakeholder status report prepared by the Scrum Master.

How the community answered

(31 responses)
  • A
    84% (26)
  • B
    10% (3)
  • C
    3% (1)
  • D
    3% (1)

Explanation

One of the key pillars that support the empirical process control is Transparency. Transparency will help manage stakeholder expectations and allow the teams to effectively adapt if and when

Topics

#stakeholder communication#transparency#Product Backlog#release forecasting