PSM-I · Question #242
PSM-I Question #242: Real Exam Question with Answer & Explanation
The correct answer is D: All answers apply.. According to the Scrum Guide, changing the terminology of Scrum may have negative consequences, such as losing the benefits of Scrum, not understanding what has changed, or having very little change at all. Therefore, all answers apply to this question. The Scrum Guide recommends
Question
An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)
Options
- AWithout a new vocabulary as a reminder of the change, very little change may actually happen.
- BThe organization may not understand what has changed within Scrum and the benefits of Scrum
- CManagement may feel less anxious.
- DAll answers apply.
Explanation
According to the Scrum Guide, changing the terminology of Scrum may have negative consequences, such as losing the benefits of Scrum, not understanding what has changed, or having very little change at all. Therefore, all answers apply to this question. The Scrum Guide recommends using the same terminology as in the guide to avoid confusion and misunderstanding.
Topics
Community Discussion
No community discussion yet for this question.