When preparing for a Cortex XSOAR proof of value (POV), which task should be performed before the evaluation is requested?

The correct answer is D. Gathering a list of the different integrations that will need to be configured. See the full explanation below for the reasoning.

Question

When preparing for a Cortex XSOAR proof of value (POV), which task should be performed before the evaluation is requested?

Options

  • AEnsuring that the customer has single sign-on (SSO) configured in their environment
  • BBuilding out an executive-level proposal detailing the product capabilities
  • CPlanning for every different use case the customer has for the solution
  • DGathering a list of the different integrations that will need to be configured

How the community answered

(57 responses)
  • A
    7% (4)
  • B
    14% (8)
  • C
    4% (2)
  • D
    75% (43)