Who decides the system architecture of a product developed using Scrum? (choose the best answer)
The correct answer is C. The Developers with input from the Scrum Team and others.. In Scrum, architecture decisions are made collectively by the Developers with input from the Scrum Team and stakeholders. This aligns with the principle of cross-functionality and collective
Refactoring and Design
Question
Who decides the system architecture of a product developed using Scrum? (choose the best answer)
Options
- AThe Architect chosen by the Scrum Team.
- BThe software architect assigned to the Scrum Team.
- CThe Developers with input from the Scrum Team and others.
- DThe Chief Architect.
How the community answered
(36 responses)- B3% (1)
- C92% (33)
- D6% (2)
Explanation
In Scrum, architecture decisions are made collectively by the Developers with input from the Scrum Team and stakeholders. This aligns with the principle of cross-functionality and collective