PSD · Question #140
PSD Question #140: Real Exam Question with Answer & Explanation
The correct answer is D. The Developers.. According to the Scrum Guide, Developers are responsible for all activities required to produce a Done Increment, including testing. While other roles may contribute insights, the team ensures quality through their combined skills.
Question
Who creates tests on a Scrum Team? (choose the best answer)
Options
- AThe Scrum Master.
- BThe Product Owner.
- CQuality Assurance Specialists.
- DThe Developers.
Explanation
According to the Scrum Guide, Developers are responsible for all activities required to produce a Done Increment, including testing. While other roles may contribute insights, the team ensures quality through their combined skills.