PROFESSIONAL-CLOUD-DEVOPS-ENGINEER · Question #152
PROFESSIONAL-CLOUD-DEVOPS-ENGINEER Question #152: Real Exam Question with Answer & Explanation
The correct answer is C: Identify recommended reliability improvements to the service to be completed before handover.. In SRE practice, if a Production Readiness Review reveals that a service cannot meet its defined SLOs, the correct next step is to identify specific reliability improvements and require them to be completed before the handover proceeds. This protects production reliability and ma
Question
You are part of an organization that follows SRE practices and principles. You are taking over the management of a new service from the Development Team, and you conduct a Production Readiness Review (PRR). After the PRR analysis phase, you determine that the service cannot currently meet its Service Level Objectives (SLOs). You want to ensure that the service can meet its SLOs in production. What should you do next?
Options
- AAdjust the SLO targets to be achievable by the service so you can bring it into production.
- BNotify the development team that they will have to provide production support for the service.
- CIdentify recommended reliability improvements to the service to be completed before handover.
- DBring the service into production with no SLOs and build them when you have collected
Explanation
In SRE practice, if a Production Readiness Review reveals that a service cannot meet its defined SLOs, the correct next step is to identify specific reliability improvements and require them to be completed before the handover proceeds. This protects production reliability and maintains the integrity of the SLO commitments. Lowering SLOs to match poor performance (A) undermines user trust. Pushing support back to the dev team (B) avoids the problem rather than solving it. Bringing the service in with no SLOs (D) leaves both users and the SRE team with no measurable standard to uphold.