PRINCE2-PRACTITIONER · Question #206

In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator

The correct answer is B. Project support. Explanation/Reference:

Quality

Question

In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator

Options

  • AProject manager
  • BProject support
  • CTeam Manager
  • DProject Assurance

How the community answered

(59 responses)
  • A
    3% (2)
  • B
    81% (48)
  • C
    5% (3)
  • D
    10% (6)

Explanation

Explanation/Reference:

Topics

#quality review technique#administrator role#project support#quality roles