nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #121

There are two time driven controls in PRINCE2, which are they?

The correct answer is B. Highlight and Checkpoint Reports. Explanation/Reference:

Progress

Question

There are two time driven controls in PRINCE2, which are they?

Options

  • AHighlight and End Stage Reports
  • BHighlight and Checkpoint Reports
  • CCheckpoint and End Project Reports
  • DHighlight and Lessons Reports

How the community answered

(16 responses)
  • A
    13% (2)
  • B
    81% (13)
  • C
    6% (1)

Explanation

Explanation/Reference:

Topics

#time-driven controls#Highlight Reports#Checkpoint Reports#progress reporting

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice