Which statement about the 'keep teams stable' target is CORRECT?

The correct answer is C. It is required in order to allow the team to self-organize. You've hit your limit · resets 5am (America/New_York)

People and Interactions

Question

Which statement about the ‘keep teams stable' target is CORRECT?

Options

  • AIt ensures that the level of quality is protected
  • BIt will lead to a lower cost of ownership
  • CIt is required in order to allow the team to self-organize
  • DIt results in the earth delivery of a minimum viable product

How the community answered

(65 responses)
  • A
    2% (1)
  • B
    8% (5)
  • C
    88% (57)
  • D
    3% (2)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#PRINCE2 Agile targets#stable teams#self-organization