What should be decided when configuring PRINCE2 effectively?
The correct answer is C. What to significantly change to create the right blend. You've hit your limit · resets 5am (America/New_York)
PRINCE2 Agile Overview and Rationale
Question
What should be decided when configuring PRINCE2 effectively?
Options
- AWhat to remove and where to add guidance
- BWhere to put the emphasis and where to add guidance
- CWhat to significantly change to create the right blend
- DWhich areas are not enabled to work with agile
How the community answered
(24 responses)- A4% (1)
- B17% (4)
- C71% (17)
- D8% (2)