Question
Which is a reason for releasing a product into a staging area?
Options
- AIt enables the faster delivery of changes
- BIt supports regulatory compliance checking
- CIt enables a phased Waterfall approach
- DIt supports management by exception
How the community answered
(21 responses)- A5% (1)
- B76% (16)
- C5% (1)
- D14% (3)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#staging area#release management#regulatory compliance#deployment