Which process can take place during a release review workshop?
The correct answer is B. Managing product delivery. You've hit your limit · resets 5am (America/New_York)
Managing Product Delivery Process
Question
Which process can take place during a release review workshop?
Options
- AControlling a stage
- BManaging product delivery
- CManaging a stage boundary
- DDirecting a project
How the community answered
(37 responses)- A5% (2)
- B84% (31)
- C3% (1)
- D8% (3)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#release review workshop#managing product delivery#PRINCE2 processes#agile ceremonies