PRINCE2
PRINCE2-AGILE-FOUNDATION · Question #24
How should product-based planning be used as part of PRINCE2 Agile?
The correct answer is D. To plan by focusing on the features required. You've hit your limit · resets 5am (America/New_York)
Plans Theme
Question
How should product-based planning be used as part of PRINCE2 Agile?
Options
- ATo track progress against the team plan
- BTo create the project plan using empiricism
- CTo enable team planning to be predictive
- DTo plan by focusing on the features required
How the community answered
(14 responses)- B7% (1)
- C7% (1)
- D86% (12)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#product-based planning#feature-driven planning#plans theme#PRINCE2 Agile
Community Discussion