How should product-based planning be used as part of PRINCE2 Agile?

The correct answer is D. To plan by focusing on the features required. You've hit your limit · resets 5am (America/New_York)

Plans Theme

Question

How should product-based planning be used as part of PRINCE2 Agile?

Options

  • ATo track progress against the team plan
  • BTo create the project plan using empiricism
  • CTo enable team planning to be predictive
  • DTo plan by focusing on the features required

How the community answered

(14 responses)
  • B
    7% (1)
  • C
    7% (1)
  • D
    86% (12)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#product-based planning#feature-driven planning#plans theme#PRINCE2 Agile