Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?
The correct answer is A. It should always be appropriate to the needs of the project. You've hit your limit · resets 5am (America/New_York)
Risk Management
Question
Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?
Options
- AIt should always be appropriate to the needs of the project
- BIt should always be addressed during the daily stand-ups
- CIt should always be carried out formally
- DIt should always be carried out informally
How the community answered
(43 responses)- A93% (40)
- C5% (2)
- D2% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#risk management#PRINCE2 Agile#project governance#flexibility