Which statement about the 'embrace change' target is CORRECT?
The correct answer is D. It degrades the performance of the features that are delivered. You've hit your limit · resets 5am (America/New_York)
PRINCE2 Agile Targets
Question
Which statement about the ‘embrace change' target is CORRECT?
Options
- AIt re-establishes team dynamics when a new member joins the team
- BIt trades user stories for those of a similar size
- CIt results in the late delivery of the minimum viable product
- DIt degrades the performance of the features that are delivered
How the community answered
(59 responses)- A3% (2)
- B8% (5)
- C14% (8)
- D75% (44)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#embrace change#PRINCE2 Agile targets#features#quality