In an agile context, who is accountable for managing risks at the delivery level?

The correct answer is A. The team manager. You've hit your limit · resets 5am (America/New_York)

Roles and Responsibilities

Question

In an agile context, who is accountable for managing risks at the delivery level?

Options

  • AThe team manager
  • BThe project manager
  • CThe project board
  • DThe project team

How the community answered

(16 responses)
  • A
    88% (14)
  • B
    6% (1)
  • D
    6% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)