PRINCE2-AGILE-FOUNDATION · Question #111

What needs to happen when new detailed requirements are added to a timebox?

The correct answer is A. Requirements of a similar level of effort should be removed. You've hit your limit · resets 5am (America/New_York)

Flexible Delivery

Question

What needs to happen when new detailed requirements are added to a timebox?

Options

  • ARequirements of a similar level of effort should be removed
  • BMore people should be added to the delivery team
  • CThe delivery milestones should be reviewed and re-planned
  • DFormal change control should be applied

How the community answered

(38 responses)
  • A
    84% (32)
  • B
    8% (3)
  • C
    3% (1)
  • D
    5% (2)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#timebox management#scope change#requirements prioritization#agile planning