How does the change theme regard change in PRINCE2 Agile?
The correct answer is D. As inevitable. You've hit your limit · resets 5am (America/New_York)
Change Theme
Question
How does the change theme regard change in PRINCE2 Agile?
Options
- AAs disruptive
- BAs something to be avoided
- CAs a necessity
- DAs inevitable
How the community answered
(62 responses)- A2% (1)
- B8% (5)
- C3% (2)
- D87% (54)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#change theme#PRINCE2 Agile#attitude to change#inevitability of change