In which process should the project manager FIRST assess the suitability of using agile?

The correct answer is C. Starting up a project. You've hit your limit · resets 5am (America/New_York)

Starting Up a Project

Question

In which process should the project manager FIRST assess the suitability of using agile?

Options

  • AControlling a stage
  • BInitiating a project
  • CStarting up a project
  • DManaging a stage boundary

How the community answered

(49 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    94% (46)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#agile suitability assessment#Starting Up a Project#PRINCE2 processes#project manager role