nerdexam
PMIPMI

PMP · Question #961

PMP Question #961: Real Exam Question with Answer & Explanation

The correct answer is C: Revisit the user story of the similar requirement, learn about its story points and velocity, and. To provide a rough estimate for a new requirement similar to a past one, the product owner should refer to the user story of the similar past requirement, including its story points and the team's velocity.

Submitted by chen.hong· Apr 18, 2026Process

Question

A customer approaches the product owner with a new requirement and asks for a rough estimation to implement it. The outline of the task would be similar to a prior deliverable. What should the product owner do to properly inform the customer?

Options

  • AAnalyze the current backlog and the backlog refinement to determine a gap for fulfilling the
  • BCheck the work breakdown structure (WBS) and the cost estimation for the similar requirement
  • CRevisit the user story of the similar requirement, learn about its story points and velocity, and
  • DRefer to the lessons learned register where the experience and effort of former requirements

Explanation

To provide a rough estimate for a new requirement similar to a past one, the product owner should refer to the user story of the similar past requirement, including its story points and the team's velocity.

Common mistakes.

  • A. Analyzing the current backlog and refinement primarily helps in prioritizing and understanding current work, not directly in estimating a new, similar requirement based on past effort.
  • B. Work Breakdown Structure (WBS) and cost estimations are typically associated with predictive project management and detailed planning, which is not suitable for a "rough estimation" in an agile context when similarity to past work is the key.
  • D. The lessons learned register contains valuable insights but does not directly provide the quantitative metrics like story points and velocity needed for a rough estimation of a new task based on a similar past task's effort.

Concept tested. Agile estimation using story points and velocity

Topics

#Agile Estimation#Story Points#Velocity#Product Owner Role

Community Discussion

No community discussion yet for this question.

Full PMP PracticeBrowse All PMP Questions