PMI-ACP · Question #630
PMI-ACP Question #630: Real Exam Question with Answer & Explanation
The correct answer is B: It prevents a wasteful buildup of requirements inventory that may never be processed. Rolling wave planning (also called progressive elaboration) deliberately plans near-term work in detail while keeping future work at a high level, updating the plan as more is known. The key benefit to communicate to management is that this prevents 'requirements inventory' waste
Question
Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project. How should the agile practitioner explain to senior management the benefits of this approach?
Options
- AIt ensures a consistent level of details is available in the project schedule
- BIt prevents a wasteful buildup of requirements inventory that may never be processed
- CIt provides a concrete definition of project scope, cost and duration
- DIt allows the team to lock down the stories to be included in a release
Explanation
Rolling wave planning (also called progressive elaboration) deliberately plans near-term work in detail while keeping future work at a high level, updating the plan as more is known. The key benefit to communicate to management is that this prevents 'requirements inventory' waste - spending time and effort detailing requirements months in advance that may change, be de-prioritized, or never be built. Option A is incorrect because rolling wave intentionally maintains different levels of detail at different time horizons - consistent detail is not the goal. Option C is incorrect because rolling wave does not lock in scope, cost, or duration for the whole project. Option D is about locking down sprint stories, which is a different concept.
Topics
Community Discussion
No community discussion yet for this question.