PMI-ACP · Question #588
PMI-ACP Question #588: Real Exam Question with Answer & Explanation
The correct answer is D: Run multiple sprints before determining the sprint velocity with the team. Velocity is an empirical measure — it must be observed over actual sprints, not estimated upfront. For a newly formed team, there is no historical data to rely on. The scrum master should guide the team to run several sprints and track their actual throughput before establishin
Question
A product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?
Options
- AEngage the team to determine the sprint velocity based on previous agile projects
- BAverage the sprint velocity based on input from team members
- CShare the sprint velocity obtained from the sponsor with the team
- DRun multiple sprints before determining the sprint velocity with the team
Explanation
Velocity is an empirical measure — it must be observed over actual sprints, not estimated upfront. For a newly formed team, there is no historical data to rely on. The scrum master should guide the team to run several sprints and track their actual throughput before establishing a reliable velocity figure (D). Using velocity from previous projects (A) is inaccurate because team composition, tooling, and context differ. Averaging team members' estimates (B) is speculative and not empirical. Obtaining velocity from the sponsor (C) is inappropriate — sponsors don't determine team capacity. Empirical measurement over multiple sprints is the foundational scrum principle at play here.
Topics
Community Discussion
No community discussion yet for this question.