PMI-ACP · Question #556
PMI-ACP Question #556: Real Exam Question with Answer & Explanation
The correct answer is B: False. False — fixed price contracts are possible in Agile. Several contract models accommodate Agile's adaptive nature while maintaining cost certainty. Common approaches include fixed price per iteration (each sprint has a fixed cost), fixed price with variable scope (cost is fixed
Question
It is not possible to have a fixed price contract in Agile.
Options
- ATrue
- BFalse
Explanation
False — fixed price contracts are possible in Agile. Several contract models accommodate Agile's adaptive nature while maintaining cost certainty. Common approaches include fixed price per iteration (each sprint has a fixed cost), fixed price with variable scope (cost is fixed but lower-priority features can be deferred), and capped time-and-materials. The key is negotiating flexibility in scope rather than trying to fix scope, cost, and time simultaneously — the classic Agile 'iron triangle' trade-off.
Topics
Community Discussion
No community discussion yet for this question.